Bathroom retiling quote: specify waterproofing before the tiles go down
For a bathroom retiling job, compare the waterproofing area, material, substrate preparation, test and repair responsibility in writing before accepting a low headline price.

Start with the layer the finished bathroom hides
A bathroom retiling quote should tell you what happens to the waterproofing beneath the floor and around the wet walls. If the work removes old tiles and screed, a promise to “retile” or “waterproof” is too broad to show whether the new layer will be continuous, compatible with the substrate and tested before it is covered. Ask for a drawing or marked photograph of the area to be treated, the material system, where it turns up walls and around penetrations, the sequence of work and the evidence to be handed over. Price can be compared only after each contractor describes the same completed bathroom.
The decision is specifically about specifying and checking a retiling job. A loose toilet, a relocated drain or a leak from a supply pipe may require different work. If there is already a wet patch below, first identify the source instead of assuming the floor membrane is the culprit. The Buildings Department's maintenance guide expressly separates leaking drainage fittings, supply pipes, sealant and a failed waterproofing floor. It says the source should be identified before repair. A good quote should therefore state whether it includes diagnosis, not silently convert every damp mark into a membrane replacement.
Buildings Department domestic works FAQ
Buildings Department maintenance guide
Define demolition and the exposed base
Give each bidder the same plan: which floor and wall finishes are to be removed, whether the old bathtub or shower tray stays, where the demolition stops, and which adjoining surfaces must be protected. Ask how the contractor will inspect and prepare the exposed base before applying waterproofing. A clean new tile surface over an unstable, damp or contaminated substrate can hide the very problem the owner intended to solve. The Buildings Department guide says that reconstructing a floor waterproof layer requires removing sanitary fitments and finishes sufficiently to form a continuous construction, and that the floor should fall towards the drain rather than pond.
The contractor should identify whether the job is a complete floor rebuild or a local finish repair. Those are not interchangeable. If an existing wet-floor leak has been traced to defective floor waterproofing, the Department's guide advises reconstructing the entire waterproofing layer instead of a patch repair. If the investigation finds only a failed seal around a bath, a smaller repair might be appropriate. Do not use that distinction to diagnose from a photograph; use it to require a written reason for the proposed scope and an agreed route if opening work reveals a different cause.
Make the waterproofing extent visible in the quote
The Consumer Council found that waterproofing was commonly omitted or vaguely described in renovation quotations. In its survey, fewer than half of the contractors that identified waterproofing locations also explained the material, layer height and whether a seepage test would be performed. Require those fields in your own quote. Mark the whole floor, shower walls, bath surround, door threshold, corners, pipe penetrations and any built-in ledge that will routinely get wet. Ask how the contractor joins the floor system to vertical surfaces and protects it during subsequent tiling and fixture installation.
The Buildings Department's guideline for preventing seepage in new buildings recommends a floor membrane that turns up every bathroom wall by at least 300mm, and waterproofing on walls around a bath or shower tray to at least 1800mm. Those figures are design guidance for new buildings, not a universal statutory instruction for every existing bathroom retiling job. They can prompt a precise discussion with the professional or contractor about the actual wetting pattern and product specifications. Record the agreed extent in the contract rather than treating a generic number as a substitute for the design of this room.
Keep legal classification tied to the physical work
Simple laying of interior tiles and replacement of sanitary fitments are described by the Buildings Department as exempted building works that generally need no prior BD approval. That does not mean every bathroom renovation is exempt. Its domestic works FAQ says alterations to a toilet, bathroom or kitchen with associated drainage work follow the Minor Works Control System, with prescribed registered contractors and notifications before or after work as applicable. Structural alterations take a different route requiring professional assessment and approval. The exact classification must follow what is physically removed or changed, not the contractor's label “bathroom refresh.”
Ask whether the quote includes moving a floor drain, altering a waste pipe, changing a structural wall, or merely replacing finishes in their existing locations. If the design changes during demolition, pause and classify the new work before authorising it. The Department also advises checking approved plans, minor works records, deed restrictions and management requirements. Management permission for access or debris movement does not replace a statutory works process; equally, a lawful building works classification does not waive the building's actual site rules.
Agree inspection points before they disappear
The most valuable check occurs while the work is still visible. Specify who photographs the bare base after demolition, the prepared corners and penetrations, each waterproofing stage required by the manufacturer's system, and the finished layer before screed or tiles conceal it. State who may inspect and approve the stage, what the installer will do if a defect is found, and when work may continue. If water testing is proposed, agree its method, location, timing, responsible person and record. The Buildings Department notes ponding and spray tests among methods used in seepage investigations, but a test result must be interpreted for the actual construction and suspected source.
Do not invent a universal ponding duration or promise that a single dry ceiling proves a bathroom is permanently leak-free. Follow the specified product, professional design and site conditions. If there is a neighbour below, arrange lawful, respectful access and agree what evidence can be obtained. Record whether a failed test is retreated and retested before covering, rather than charging for a new layer without a closeout standard. A photo set, signed stage record and test note make a later defect much easier to investigate than a finished tile image alone.
Compare two quotations on the same deliverable
Suppose Quote A offers “remove old tiles and re-tile bathroom, waterproof included” for a low total. Quote B states demolition area, substrate repair allowance, named waterproofing system, floor and wall extent, inspection stage, test method, tile and grout specification, waste disposal, payment milestones and defects response. Quote B may cost more or less once both cover the same work; the initial totals do not tell you. Ask Quote A to fill the missing fields, then compare exclusions and contingencies. This is an illustrative procurement comparison, not a live price claim.
The Consumer Council advises consumers to get detailed quantities, unit rates, labour and materials, payment terms and contract period in writing. Ask what “labour and materials” actually contains, whether tiles and trim are supplied by the owner, and how breakage or discontinued tiles are handled. Define a written variation process: photograph the finding, explain the proposed change, give a priced effect on time and cost, and obtain agreement before covering or replacing anything outside the scope. This is especially useful when a hidden damp base appears after demolition.
Handover and later symptoms
Before final payment, compare the finished area with the marked scope and stage photos. Check that floor falls lead to the intended drain without persistent ponding, tile edges and joints are sound, sealant is complete at sanitary fixtures, and access panels remain usable. Retain product details, the contractor's written method, site photos, test record, invoice, and any required minor works documents. If fixed electrical points or plumbing services were changed as a separate part of the job, retain their respective completion evidence too. A clean-looking bathroom cannot prove the buried layer was built as specified. Also identify the exact product system and retain its instructions, because primer, membrane, protection and tile adhesive must be compatible in the selected system. If the contractor proposes a substitute after work starts, ask for the reason and the revised method in writing before it is covered. Do not replace an inspection stage with a generic guarantee period: a guarantee may set a remedy later, while the stage record shows what was actually built now. The intermediate record fills that gap.
If a stain later appears below, do not assume the new waterproofing has failed or blame a neighbour from the stain's position alone. Reopen the symptom file with dates, photos and usage pattern, then compare it with the actual works record and arrange a proper source investigation. The Buildings Department identifies several possible water paths in bathrooms. A defensible retiling decision is one where the owner knows the intended construction, the contractor's duty, what was inspected before concealment, and what must be revisited if the original concern returns.