First-hand flat defects after handover: send a written notice
Record each defect, serve the vendor a written notice within the contractual period after completion, and reinspect the actual repair before closing an item.

Send a dated written notice, then track the repair
If you discover a defect after taking a first-hand Hong Kong flat, document the exact item and notify the vendor in writing promptly. The mandatory agreement provision described by the SRPA covers defects in the property and the fittings, finishes or appliances listed in the agreement when they are caused otherwise than by the buyer's act or neglect. The written notice must be served within 6 months after the date of completion of the sale and purchase. That clock starts at contractual completion, not at the day you finish unpacking or the first time a contractor can visit. Ask your solicitor to confirm the date and notice method in your signed agreement.
A telephone call to a handover desk can help arrange access, but it is not a reliable substitute for a written notice. Give each defect a location, a factual description, a discovery date and evidence that allows another person to find and reproduce it. Request an acknowledgement and a proposed inspection or rectification date. Keep a copy of the notice and proof of delivery. The vendor must remedy a covered defect at its own cost as soon as reasonably practicable after receiving a qualifying notice; the statute does not mean every issue will be repaired on the day it is reported.
Anchor the deadline to the transaction documents
Find the date of completion in the agreement, your solicitor's completion statement and the actual transaction record. Note the calendar date that falls 6 months after it, but arrange to serve the notice comfortably before the deadline. If the flat was handed over later, or the household delayed moving in, those facts do not automatically move the statutory notice period. The exact notice address and service mechanism in the agreement matter too. Ask your solicitor how to comply with them; sending a casual message to a salesperson may not be the same as serving the vendor.
Treat the brochure's defect liability period and the signed agreement as documents to reconcile, not two interchangeable promises. The first-hand sales rules require the brochure to state the duration of the vendor's liability to make good defects as provided in the agreement. Retain the brochure version for the property and the contractual schedule of fittings, finishes and appliances. If marketing material appears to promise a different or longer service, ask the vendor to explain it in writing and ask a solicitor to assess whether it is part of the contract. Do not quietly assume every manufacturer's separate warranty changes the vendor's contractual deadline.
Inspect systematically without causing a new defect
Before moving furniture against walls or starting renovations, walk each room with the latest sales brochure, the agreement's fittings schedule and the handover documents. Photograph wide views to locate the item and close views to show the symptom. Note whether a window opens as represented, whether a cabinet door aligns, whether a tap leaks under ordinary use, and whether an appliance supplied under the agreement performs its normal basic function. Use a reasonable, permitted test and stop when a safety concern appears. Do not dismantle electrical or gas equipment, flood a bathroom to test waterproofing, or damage finishes merely to create evidence.
Distinguish a visible symptom from its cause. A stain might involve plumbing, external rain or an installation fault; the buyer can describe the position and timing without diagnosing it. If a contractor says the issue is in a common part rather than the individual property, ask for a written explanation and a management contact. The vendor's defect clause and the building manager's maintenance route may involve different work. Keep them connected in the record, but do not let a referral between teams erase the original notice date.
Make the notice useful to a repair team
A useful entry reads like a work order: room and exact position, item shown in the brochure or agreement if relevant, observable fault, conditions under which it occurs, first date seen, photographs or short video, and the remedy requested. 'Bathroom leak' is vague; 'water appears at the lower cabinet joint after ordinary use of the basin tap' gives an inspector somewhere to start. Include the flat identifier and a contact for access, but avoid sending unrelated personal documents. Number the items so replies, visits and closure can be matched to each defect.
Ask the vendor to acknowledge each item as reported, identify the team that will inspect it, and state what additional evidence is needed. If a repair is proposed, obtain the scope and access arrangements in writing. If the vendor says an item was damaged by the buyer, ask for the specific basis and record your response, photographs taken at handover and any earlier correspondence. The statutory clause concerns defects not caused by the buyer's act or neglect; a disputed cause may require expert and legal assessment. A neat chronology makes that assessment possible without pretending the buyer can settle causation by assertion.
Do not combine unrelated faults into one item labelled 'poor workmanship'. A sticking bedroom window, a leaking sink joint and a cracked tile may have different investigators and different completion dates. Separate entries also let you accept one finished repair without surrendering the unresolved others. If you discover a new problem during a repair visit, create a new dated entry and send it by the required written route. A contractor's informal acknowledgement at the door should not be the only record of a newly discovered defect.
Keep urgent safety and water problems moving
Written notice preserves the defect trail, but it does not require a household to keep using unsafe equipment while it waits. Stop using an appliance that appears dangerous; if there is active water, electrical danger or suspected gas leakage, take appropriate immediate safety steps and contact the responsible emergency or qualified service. Record what happened and tell the vendor in writing as soon as practicable. A quick isolation or emergency action may prevent further loss; ask the professional to identify what was done so later repair responsibility is traceable.
Coordinate access with management where a common pipe, façade or other shared element may be involved. Ask the vendor or manager to specify who investigates the source and who makes good the flat. If repair requires opening finishes, agree how the surfaces and affected fittings will be reinstated and tested. Avoid accepting a repaint as full closure of a recurring dampness problem without evidence of the cause and its remedy. The handover defect process is a sequence of diagnosis, agreed work and reinspection, not a single photograph of a tidier wall.
Compare two hypothetical defect files
Imagine Buyer A completes on 2026-11-15, discovers a chipped bathroom tile at handover and sends a written itemised notice with photographs on 2026-11-18. Buyer B completes on the same date, calls a sales representative several times about a similar chip, and sends a written note only after the 6-month period has passed. These dates are hypothetical. Buyer A has a clear timely notice and condition record. Buyer B may still need legal advice about any other rights, but should not assume calls alone satisfy the mandatory written-notice route. The contrast is about documentation and timing, not a promise that either claim automatically succeeds.
Now change the issue to a leak that appears only during rain. Both buyers should record the weather, location and recurrence and ask for an investigation rather than simply demanding a cosmetic patch. If the vendor's team visits and finds no active water on a dry day, retain the original notice and request a follow-up method for the conditions that produced the leak. A repair ticket marked 'attended' is not the same as an evidence-based resolution. Use the same item number and photos across each visit so a new staff member can follow the history.
Reinspect, close and escalate on evidence
After work, inspect the original symptom under a sensible comparable condition, record the date and ask for the work details. A replacement cabinet hinge can be checked by ordinary opening and closing; a concealed leak may require a professional test and a later observation period. Do not sign an unqualified 'all defects resolved' acknowledgement while material items remain open. If the vendor asks for a sign-off, list only the items actually retested and note those that still need investigation. Keep a consolidated folder of the brochure, agreement, notices, delivery evidence, replies, work records and reinspection photographs.
If the vendor does not respond or the remedy is disputed, send a concise written follow-up identifying the original notice and outstanding items. SRPA says a buyer who considers that the vendor has not fulfilled the contractual term may consider civil proceedings, seek professional and legal advice, or make an enquiry with the Consumer Council. The choice depends on the evidence and actual agreement; an article cannot decide liability or damages for a particular case. When comparing new flats on Houseline, make this post-completion record plan part of the purchase decision, especially if the buyer expects to move in immediately after keys are issued.